Put Inženjering from Podgorica has won the tender to prepare the conceptual design for the Nikšić – Žabljak – Pljevlja expressway, offering the most favorable price of EUR 192.39 thousand. The project is being implemented by Monteput, and the total length of the new road will be 96 kilometers, including the construction of bridges and tunnels.
Key stages and contractors of Put Inženjering
The future route will be divided into three subsections:
- Nikšić – Šavnik,
- Šavnik – Žabljak,
- Žabljak – Pljevlja.
As subcontractors, Geot (Podgorica) and Geotehnika Montenegro (Nikšić) have been engaged for the project.
Tender and design details
The tender was announced on December 24, 2024, applications were accepted until January 27, 2025, and its initial estimated value was EUR 205,000. During the review of bids, Monteput rejected the joint bid from Decom Group and Louis Berger due to non-compliance with the requirements — the documentation did not clearly define the division of responsibilities for bridge design.
The main goal of the design documentation is to determine the optimal route taking into account the terrain, the environment, and economic feasibility. The design work will take six months from the momentthe contract is signed.
Main characteristics of the route
- Maximum speed — 100 km/h (with the possibility of reduction on difficult sections).
- Crossing key natural features — the Komarnica and Tara canyons, as well as Durmitor National Park.
- Connection to major highways — the expressway will connect Nikšić, Žabljak and Pljevlja with the Bar – Boljare motorway and the Adriatic-Ionian highway.